Primat Construction CC v Nelson Mandela Bay Metropolitan Municipality
| Jurisdiction | South Africa |
| Court | Supreme Court of Appeal |
| Judge | Lewis JA, Tshiqi JA, Saldulker JA, Swain JA and Molemela AJA |
| Judgment Date | 01 June 2017 |
| Citation | 2017 (5) SA 420 (SCA) |
| Hearing Date | 01 June 2017 |
| Docket Number | 1075/2016 [2017] ZASCA 73 |
| Counsel | P Ellis SC (with P Ellis Jr) for the appellant. SC Rorke SC (with GJ Gajjar) for the respondent. |
Lewis JA (Tshiqi JA, Saldulker JA, Swain JA and Molemela AJA concurring):
[1] This appeal, against a decision of a full court on appeal (in the C Eastern Cape Division before Lowe J, Chetty J and Ndzondo AJ), turns on whether a party to a contract, who has elected not to accept a repudiation of the contract by the other party, may, in the face of the persistent and unequivocal intention of the other not to be bound, change its stance and cancel and sue for damages for breach of contract. D The trial court (Revelas J) had held that where the repudiation had continued, the innocent party was entitled to change its election and cancel the contract. The full court, reversing this decision, held that there had to be another manifest act of repudiation before the innocent party could change the election, and upheld the appeal. The appeal to this court is with its special leave. E
[2] In 2010 the appellant, Primat Construction CC (Primat), concluded a contract, pursuant to a tender, for the upgrade of roads in Motherwell, Port Elizabeth, with the respondent, the Nelson Mandela Bay Metropolitan Municipality (the Municipality). Primat was required to F reconstruct roads and supply materials. When sued by Primat for damages for breach of contract, the Municipality pleaded that it had repudiated the contract and that Primat had elected not to accept the repudiation and to abide by it, demanding specific performance. Primat, it alleged, was bound by its election and could not subsequently cancel the contract and claim damages. At their pre-trial conference, the parties agreed that only G the questions whether there had been a repudiation of the contract by the Municipality, and whether Primat was bound by its election not to accept the repudiation, should be determined at trial. The determination of quantum, if the Municipality were liable for damages, would be done later. An order to that effect was made in terms of Uniform Court Rule 33(4). H
[3] Despite a lengthy trial, the facts were largely undisputed. The project was managed by Iliso Consulting (Pty) Ltd for the Municipality. Mr A White of Iliso was appointed as the engineer to supervise the construction. I The contract was covered by the standard terms in the industry, embodied in the Special Conditions of Contract and the General Conditions of Contract for Construction Works (2004), issued by the South African Institute of Civil Engineering. The work was scheduled to commence in April 2010 and to end in November 2010. Primat was required to submit guarantees for the completion of the work from a J
Lewis JA
bank A or insurance company. Coface South African Insurance Co Ltd furnished guarantees for 10% of the contract cost (some R15,5 million) to the Municipality.
[4] There were numerous delays in the progress of the work, caused by a number of factors. These included severe storm damage, and the late B payment of an insurance claim to Primat for the damage. But delays were also caused by non-payment by the Municipality against monthly payment certificates. The completion date was extended to November 2011. On 10 November 2011 Primat wrote a letter to the Municipality advising that it was unable to proceed with the works until its financial difficulties were resolved. It undertook to resume the works when that C occurred.
[5] On 24 November 2011 White of Iliso wrote to Mr J Cola, the sole member of Primat, stating that Primat was in breach of the contract because of the slow pace of the work, and work stoppages. He continued that the Municipality might, after giving 14 days' notice in writing to D Primat, terminate the contract. On 22 December 2011 Mr S Agherdien of the Municipality wrote to Primat requesting certain information by 16 January 2012, and asking what remedial measures would be put in place to increase the work rate.
[6] E On 17 January 2012 Agherdien wrote to Primat purportedly terminating the contract with immediate effect in terms of various clauses of the contract. It is common cause that the letter did not constitute a proper termination and thus amounted to a repudiation of the contract by the Municipality. On the same day, Cola's attempts to gain access to the site were denied.
[7] F Primat responded to the purported notice of termination on 19 January 2012, pointing out that it was 'procedurally incorrect' and thus lacked validity. Cola for Primat continued: 'Primat Construction will remain servicing the contract until this matter is finalized'. Agherdien responded on 25 January, repeating that the contract was terminated G and requiring Primat to vacate the site with immediate effect.
[8] Primat in turn wrote to the Municipality on 27 January explaining that it was entitled to rectify any alleged breaches by it after being given the requisite notice, and that since Primat had not been given notice, the termination was ineffective. Cola, for Primat, advised that it had again H been denied access to the site on the day before, and that the Municipality itself was in breach of the contract.
[9] On 2 February 2012 a...
Get this document and AI-powered insights with a free trial of vLex and Vincent AI
Get Started for FreeUnlock full access with a free 7-day trial
Transform your legal research with vLex
-
Complete access to the largest collection of common law case law on one platform
-
Generate AI case summaries that instantly highlight key legal issues
-
Advanced search capabilities with precise filtering and sorting options
-
Comprehensive legal content with documents across 100+ jurisdictions
-
Trusted by 2 million professionals including top global firms
-
Access AI-Powered Research with Vincent AI: Natural language queries with verified citations
Unlock full access with a free 7-day trial
Transform your legal research with vLex
-
Complete access to the largest collection of common law case law on one platform
-
Generate AI case summaries that instantly highlight key legal issues
-
Advanced search capabilities with precise filtering and sorting options
-
Comprehensive legal content with documents across 100+ jurisdictions
-
Trusted by 2 million professionals including top global firms
-
Access AI-Powered Research with Vincent AI: Natural language queries with verified citations
Unlock full access with a free 7-day trial
Transform your legal research with vLex
-
Complete access to the largest collection of common law case law on one platform
-
Generate AI case summaries that instantly highlight key legal issues
-
Advanced search capabilities with precise filtering and sorting options
-
Comprehensive legal content with documents across 100+ jurisdictions
-
Trusted by 2 million professionals including top global firms
-
Access AI-Powered Research with Vincent AI: Natural language queries with verified citations
Unlock full access with a free 7-day trial
Transform your legal research with vLex
-
Complete access to the largest collection of common law case law on one platform
-
Generate AI case summaries that instantly highlight key legal issues
-
Advanced search capabilities with precise filtering and sorting options
-
Comprehensive legal content with documents across 100+ jurisdictions
-
Trusted by 2 million professionals including top global firms
-
Access AI-Powered Research with Vincent AI: Natural language queries with verified citations
Unlock full access with a free 7-day trial
Transform your legal research with vLex
-
Complete access to the largest collection of common law case law on one platform
-
Generate AI case summaries that instantly highlight key legal issues
-
Advanced search capabilities with precise filtering and sorting options
-
Comprehensive legal content with documents across 100+ jurisdictions
-
Trusted by 2 million professionals including top global firms
-
Access AI-Powered Research with Vincent AI: Natural language queries with verified citations
Start Your 7-day Trial
-
Remedies, repentance and the doctrine of election in South African contract law
...practice and legal developments around the world, and whether it should be retained in South African law in its current form.5 2017 (5) SA 420 (SCA).6 The terminology of ‘ssured breach’ is that popularised by A Cockrell ‘Breach of contract’ in Zimmermann & Visser Southern Cross (n 1) 303. ......
-
The law relating to executory contracts in South Africa during business–rescue proceedings
...GF Lubbe & MFB Reinecke Contract: General Principles5 ed (2016) 383.70 Nash v Golden Dumps (Pty) Ltd 1985 (3) SA 1 (A) at 22D–F.71 2017 (5) SA 420 (SCA) para 22.72 Solomon & Boltar op cit note 48 at 27. © Juta and Company (Pty) 50 (2017) 3 (2) JOURNAL OF CORPORATE AND COMMERCIAL LAW & PRA......
-
Remedies, repentance and the doctrine of election in South African contract law
...practice and legal developments around the world, and whether it should be retained in South African law in its current form.5 2017 (5) SA 420 (SCA).6 The terminology of ‘ssured breach’ is that popularised by A Cockrell ‘Breach of contract’ in Zimmermann & Visser Southern Cross (n 1) 303. ......
-
The law relating to executory contracts in South Africa during business–rescue proceedings
...GF Lubbe & MFB Reinecke Contract: General Principles5 ed (2016) 383.70 Nash v Golden Dumps (Pty) Ltd 1985 (3) SA 1 (A) at 22D–F.71 2017 (5) SA 420 (SCA) para 22.72 Solomon & Boltar op cit note 48 at 27. © Juta and Company (Pty) 50 (2017) 3 (2) JOURNAL OF CORPORATE AND COMMERCIAL LAW & PRA......